An office relocation checklist is usually written by facilities, and it is good at the things facilities controls. Lease dates, furniture, signage, movers, parking. The technology section tends to be four bullet points added late by somebody who was not in the room. That is the half that decides whether anybody can work on the Monday after the move.
- Connectivity lead times are the long pole. Order before you sign anything.
- Count what is actually in the building before you plan what moves.
- Decide early what does not come with you. Moving old kit costs more than it is worth.
- Name an IT owner with a veto on the move date.
- Anything retired in the move still needs a documented wipe.
- Plan for the people who will not be in the new office at all.
Why the office relocation checklist stops at the furniture
Facilities owns the move, which is correct. Facilities also writes the checklist, which is where the problem starts.
A good facilities checklist covers the lease handover, dilapidations, the furniture plan, access control, signage and the movers. All of it necessary.
Best tools for HR Operations
Technology appears near the end as a short list: internet, phones, printers, move the servers. Each of those is a project rather than a line item, and two of them have lead times measured in months.
The ordering mistake
The move date is usually set by the lease, then everything else is fitted around it. Connectivity does not fit around anything. A business line into a new building can take weeks or months depending on what is already in the ground.
So the single most useful change to any office relocation checklist is to move connectivity from the technology section to the property section, and order it at the point you shortlist buildings rather than the point you sign.
Count what is actually there
Most moves are planned against an assumed inventory. The assumption is always generous.
Before planning what moves, walk the building and count. Not from the asset register, which we have already established drifts, but physically, once.
| Category | What to record | Why it matters at a move |
|---|---|---|
| Monitors and docks | Count and condition | Biggest volume, lowest value, often binned |
| Desk phones | Count, and whether anyone uses them | Frequently moved and never plugged in again |
| Printers and scanners | Count, lease or owned | Leased units have contractual move terms |
| Network hardware | Switches, APs, cabling | Rarely reusable in a different layout |
| On-site servers or NAS | Anything with data on it | Needs a plan, not a van |
| Unassigned laptops | Count and age | Usually more than anyone expects |
The last row is the interesting one. Most offices contain a drawer of laptops nobody has issued, several of them old enough that moving them is not worth the handling.
That count is also a free asset reconciliation, which is otherwise hard for a distributed company. Our note on equipment depreciation covers what to do with the difference you find.
Decide what does not come with you
Moving equipment costs money per item regardless of what the item is worth. A five year old monitor costs the same to wrap, load and unload as a new one.
So the useful question is not what moves, it is what does not.
Three honest categories.
- Retire it. Anything past its refresh date, anything broken, anything nobody has used in a year.
- Send it to a person. If somebody is now mostly remote, their monitor is more useful at their desk than in a box.
- Move it. Everything that survives the first two questions.
The second category is the one people forget, and it is usually the best answer for a hybrid team. A monitor already owned, shipped directly to the person who was using it, is cheaper than moving it to an office they visit twice a month and then buying them one for home.
Retiring properly
Anything with storage in it needs a documented wipe rather than a trip to a skip. NIST Special Publication 800-88 on media sanitization sets out what sanitisation actually means, and the distinction between clearing, purging and destroying matters when the device held company data.
the EPA guidance on electronics stewardship covers the disposal route itself. A move is the moment most companies generate their largest single volume of e-waste, and it is worth routing through something that produces a certificate.
The people who will not be in the new office
Every office move now has a category that did not exist a decade ago: staff who were attached to the old building and will not meaningfully use the new one.
Sometimes that is the stated plan. More often it is the quiet consequence of moving the office somewhere with a longer commute.
Either way, those people need a home setup, and the move is the moment to sort it rather than six weeks later when the complaints arrive.
the OSHA computer workstation guidance describes what a properly arranged workstation involves, which is the same wherever the desk is. the UK guidance on homeworking expenses and benefits covers how the UK treats homeworking expenses and benefits, and equivalent rules elsewhere differ, so check before setting an allowance.
Equipment that has to reach homes
Shipping monitors and chairs to individual addresses is a different operation from moving an office, and facilities contractors are rarely set up for it. For distributed teams this is where a partner is genuinely useful: RemoAsset handles delivery to individual addresses and collection from them later, which is the half a moving company will not do.
The decision table
The right amount of planning depends on what kind of move it is.
| Situation | Scale | Setup | Primary pain | Recommended starting point |
|---|---|---|---|---|
| Same city, similar size | Under 50 staff | Cloud-based, no servers | Connectivity lead time | Order the line at shortlist stage |
| Downsizing to a smaller office | 50 to 200 | Hybrid already | Surplus equipment | Ship to homes, retire the rest |
| Closing an office entirely | Any | Going fully remote | Nothing has a destination | Plan recovery and disposal, not a move |
| Office with on-site infrastructure | Any | Servers or comms room | Downtime window | Separate project, separate owner |
| Moving countries | Series B+ | New entity | Customs on every asset | Buy new locally, dispose in place |
Row five surprises people. Moving a fleet across a border is a customs exercise per device, and for anything more than a year old it is usually cheaper to dispose locally and buy fresh in the new market.
Name an IT owner with a veto
The single change that prevents most move-day failures is naming one person accountable for technology working on the first morning, and giving them the ability to object to the date.
The veto gets negotiated away, because the lease date feels immovable. Sometimes it genuinely is. But an accountable person without a veto can only predict the failure, not prevent it.
The two dates that matter
The connectivity order date, which should be at shortlist, and the equipment cut-off, after which nothing new is ordered to the old address.
That second one is small and saves a surprising amount of mess. Without it, kit keeps arriving at a building you no longer occupy for weeks after the move.
For how that ownership question plays out when the business event is a merger rather than a move, see our piece on equipment in an acquisition.
RemoAsset delivers equipment to homes and recovers it later, which is the part a moving company will not handle. More on device operations at HROpsLab.
Frequently asked questions
What is missing from most office relocation checklists?
The technology half, and specifically its position in the timeline. Facilities writes the checklist and covers the lease, furniture, access control and movers thoroughly, then adds four technology bullets near the end. Connectivity in particular has a lead time measured in weeks or months depending on what is already in the ground, so it belongs in the property section and should be ordered when you shortlist buildings rather than when you sign.
Should we move old monitors and desk phones to a new office?
Usually not. Moving equipment costs roughly the same per item whatever the item is worth, so a five year old monitor costs the same to wrap, load and unload as a new one. Sort everything into retire, send to a person’s home, or move, in that order. The middle category is the one teams forget and it is often the best answer, since a monitor is more useful at the desk of someone who now works remotely.
How do we handle equipment for people who will not use the new office?
Treat it as part of the move rather than as a follow-up. Every relocation now creates a group who were attached to the old building and will not meaningfully use the new one, sometimes by plan and often because the commute changed. They need a home setup, and sorting it during the move is far cheaper than handling it individually six weeks later when the complaints start arriving.
What should happen to equipment we retire during a move?
Anything containing storage needs a documented sanitisation rather than a trip to a skip, and the distinction between clearing, purging and destroying matters when the device held company data. Route the disposal through something that produces a certificate. A move typically generates the largest single volume of electronic waste a company will ever produce, which makes it the worst moment to be informal about it.
Who should own IT during an office relocation?
One named person accountable for technology working on the first morning, with the ability to object to the move date. The veto is the part that gets negotiated away because the lease date feels fixed, and without it the accountable person can only predict the failure rather than prevent it. The two dates they should control are the connectivity order and the equipment delivery cut-off to the old address.
Is it cheaper to move equipment internationally or buy new?
For anything more than about a year old, buying new in the destination market is usually cheaper once customs is accounted for. Moving a fleet across a border is a customs exercise per device, with duty, broker fees and delay attached to each one, and the warranty and support path frequently do not travel with the hardware. Dispose in place through a certified route and buy locally.
When should we order internet for the new office?
At the point you shortlist buildings, not the point you sign the lease. Business connectivity lead times depend entirely on what infrastructure already exists at the address, and the range between a building that is already served and one that is not can be months. Asking the question during shortlisting also gives you a real comparison point between candidate buildings that the agent will not volunteer.